The general plan of realization from start to the beginning of generation in a network of solar power plant
- signing of the Land Lease Agreement;
- obtaining Technical conditions for connection to electrical networks;
- preparation of design documentation for SES;
- obtaining urban planning conditions;
- project expertise;
- approval of project documentation at SES;
- obtaining a permit to start construction;
- preparation of design documentation for connection of SES to networks;
- approval of project documentation for connection to the network;
- arrangement of electric networks for delivery of power of station in a network;
- arrangement of networks of own needs;
- delivery of metal structures;
- supply of inverters;
- delivery of photomodules;
- execution of construction and installation works on the SES site;
- execution of commissioning works of SES equipment;
- preparation of executive documentation;
- obtaining a declaration of completion of construction works;
- registration of documents for obtaining a license and a green tariff in the National Commission for Regulation of Economic Competition;
- signing of the Agreement with Energorynok.